planewave_1000
Differences
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
planewave_1000 [2023/11/08 22:21] – [PlaneWave 1000] jasonj | planewave_1000 [2024/01/27 03:32] (current) – jasonj | ||
---|---|---|---|
Line 1: | Line 1: | ||
====== PlaneWave 1000 ====== | ====== PlaneWave 1000 ====== | ||
- | We will be installing | + | We employ |
- | The telescope is an alt-az, f/6 with a corrected Dall-Kirkham optical design. It has an integrated direct drive mount system. | + | The 1-meter |
- | Here are few images of the SONG PW 1000 before being shipped to APO in November 2023. | + | ===== Commissioning ===== |
- | {{gallery> | + | |
===== Installation ===== | ===== Installation ===== | ||
+ | |||
+ | Installation was completed on January 17, and initial testing was carried out on January 18, 2024. In the photos you see PW employees Josh, Alex, and Colin. | ||
+ | |||
+ | {{gallery> | ||
+ | |||
+ | |||
+ | |||
+ | Here are few images of the SONG PW 1000 in the factory in Michigan before being shipped to APO in November 2023. | ||
+ | |||
+ | |||
+ | {{gallery> | ||
+ | |||
+ | |||
- | ===== Commissioning ===== |
planewave_1000.1699482093.txt.gz · Last modified: 2023/11/08 22:21 by jasonj