 The work breakdown structure (WBS) describes all project deliverables. The work breakdown structure (WBS) describes all project deliverables.
  
 +1 SONG in NM Construction
 +  *1.1 Project Management
 +    *1.1.1 NSF start (M)
 +    *1.1.2 WBS development and approval
 +    *1.1.3 Project schedule development and approval
 +    *1.1.4 MOU documents
 +    *1.1.5 Postdoc
 +    *1.1.6 Budget
 +    *1.1.7 Contracting
 +    *1.1.8 Reporting Documentation
 +  *1.2 Facilities
 +    *1.2.1 [[observatory_dome_and_pier|1-m dome]]
 +      *1.2.1.1 Preparation work
 +      *1.2.1.2 Telescope removal
 +      *1.2.1.3 Pier work
 +    *1.2.2 NMSU lab facility
 +    *1.2.3 APO lab facility
 +    *1.2.4 [[fiber_run|Fiber  run]]
 +      *1.2.4.1 Design
 +      *1.2.4.2 Fabrication, procurement, installation
 +  *1.3 Telescope Systems
 +    *1.3.1 [[planewave_1000#Installation|PlaneWave 1000 1-m telescope (vendor)]]
 +    *1.3.2 Monitors
 +    *1.3.3 Remote communication system
 +      *1.3.3.1 Hardware
 +      *1.3.3.2 Observatory control system (OCS)
 +      *1.3.3.3 [[software|Telescope control system]] (TCS)
 +  *1.4 Instrument Systems
 +    *1.4.1 [[song_spectrograph|SONG spectrograph]]
 +      *1.4.1.1 Optical design
 +      *1.4.1.2 Standard item procurement
 +      *1.4.1.3 Specialty item procurement
 +      *1.4.1.4 Optical table
 +      *1.4.1.5 Lab assembly
 +      *1.4.1.6 Control computers and software
 +      *1.4.1.7 Thermal enclosure
 +      *1.4.1.8 Monitors
 +      *1.4.1.9 Lab testing and acceptance
 +      *1.4.1.10 Transport to APO
 +      *1.4.1.11 Reassembly and integration
 +      *1.4.1.12 Site testing and acceptance
 +    *1.4.2 [[focal_plane_unit|Guider unit]]
 +      *1.4.2.1 Design and assembly
 +      *1.4.2.2 Lab testing and acceptance
 +      *1.4.2.3 Transport to APO
 +      *1.4.2.4 Reassembly and integration
 +      *1.4.2.5 Site testing and acceptance
 +    *1.4.3 Calibration unit
 +      *1.4.3.1 Design and assembly
 +      *1.4.3.2 Lab testing and acceptance
 +      *1.4.3.3 Transport to APO
 +      *1.4.3.4 Reassembly and integration
 +      *1.4.3.5 Site testing and acceptance
 +    *1.4.4 Solar telescope (tbd)
 +  *1.5 Network Software
 +    *1.5.1 Scheduler
 +    *1.5.2 Data handling system (DHS)
 +    *1.5.3 Monitors database and webpage
 +  *1.6 Integration, Test, and Commissioning
 +    *1.6.1 Software integration
 +    *1.6.2 First light through telescope
 +    *1.6.3 First light through spectrograph
 +    *1.6.4 Science verification
 +    *1.6.5 NSF end
 +  *1.7 Contingency
 +    *1.7.1 Cost contingency
 +    *1.7.2 Schedule contingency
 +    *1.7.3 Scope contingency
  
  
 +===== Schedule =====
  
 +A high-level picture of the construction project schedule as of August, 2023 is shown here.
 +
 +{{:manage:project_schedule.png?direct&500 |}}
 +
 +
 +===== Update / item tracking  =====
 +
 +Tasks identified February 2025:
 +
 +Spectrograph
 +  - <del>continued work on alignment, esp with "point" source</del>
 +  - <del>installation of prism</del>
 +  - <del>installation of camera</del>
 +  - <del>installation of focuser + detector</del> 
 +  - <del>testing with calibration source? solar source?</del>
 +
 +Calibration channel
 +  - <del>assembly of relay optics / stage at focal plane</del>
 +  - <del>development of calibration source : Shelyak possibility? Selectable sources by stage? Integrating sphere?</del>
 +
 +Fiber
 +  - getting long fiber run + ferrule. All circular fiber? match 125 micron cladding or not?  Fusing 50/75/125 micron cladding onto other 50 micron fiber at focal plane side?  Fusing hexagonal fiber onto circular 50 micron fiber at ferrule side?
 +  - running fiber through conduit
 +
 +Spectrograph room
 +  - <del>legs for table</del>
 +  - insulating box for spectrograph
 +  - <del>making room in APO room</del> 
 +  - <del>confirming power (UPS) and Ethernet</del>
 +  - relay/thermocouple control/computer packaging
 +  - <del>location of pump</del>
 +  - <del>more thermocouples for monitoring instrument</del>
 +
 +FPU box
 +  - cover
 +  - cabling
 +
 +Dome
 +  - lower slit control
 +  - packaging of dome control
 +  - spare computer and Raspberry Pi?
 +
 +Software
 +  - interfacing Aarhus with APO