Project Management in Construction Phase
Work Breakdown Structure
The work breakdown structure (WBS) describes all project deliverables.
1 SONG in NM Construction
Schedule
A high-level picture of the construction project schedule as of August, 2023 is shown here.
Update / item tracking
Tasks identified February 2025:
Spectrograph
continued work on alignment, esp with “point” source
installation of prism
installation of camera
installation of focuser + detector
testing with calibration source? solar source?
Calibration channel
assembly of relay optics / stage at focal plane
development of calibration source : Shelyak possibility? Selectable sources by stage? Integrating sphere?
Fiber
getting long fiber run + ferrule. All circular fiber? match 125 micron cladding or not? Fusing 50/75/125 micron cladding onto other 50 micron fiber at focal plane side? Fusing hexagonal fiber onto circular 50 micron fiber at ferrule side?
running fiber through conduit
Spectrograph room
legs for table
insulating box for spectrograph
making room in APO room
confirming power (UPS) and Ethernet
relay/thermocouple control/computer packaging
location of pump
more thermocouples for monitoring instrument
FPU box
cover
cabling
Dome
lower slit control
packaging of dome control
spare computer and Raspberry Pi?
Software
interfacing Aarhus with APO