project_status [2025/10/02 18:58] – [SONG in New Mexico Status] jasonjproject_status [2025/10/05 23:04] (current) – [SONG in New Mexico Status] 172.59.1.110
Line 1: Line 1:
 ===== SONG in New Mexico Status ===== ===== SONG in New Mexico Status =====
-(updated 5/30/2025)+(updated 10/5/2025)
  
 The SONG spectrograph is assembled and awaiting first light at Apache Point Observatory. The SONG spectrograph is assembled and awaiting first light at Apache Point Observatory.
Line 8: Line 8:
   * FIRST LIGHT! October 2, 2025   * FIRST LIGHT! October 2, 2025
   * Fiber installed in conduit. September 2025   * Fiber installed in conduit. September 2025
-  * Received optical fiber and install in conduit. July 2025+  * Received optical fibers. July 2025
          
  