=== Important dates === 4/22/2026 : liquid-cooled CCD reinstalled, chiller implemented. Stage maximum velocities reduced. Iodine cell realigned 4/17/2026 : iodine cell re-aligned. Old Maestro re-installed 4/8/2026 : replacement Maestro controller installed 4/7/2026 : new iodine cell installed. Shutter/relay installed in direct cal channel 2/05/2026 : Iodine cell flipped to test throughput 11/18/2025 : Enclosure box installed, requiring ferrule to be reseated. Spectrograph refocussed. 10/2/2025 : First light on sky! 5/29/25 : new Shelyak FIGU installed. Calibration channel mirrors adjusted. 5/8/25 : initial spectrograph (re)assembly complete at APO 4/30/25 : optical table and vibration isolation supports installed in spectrograph room