====== Project Management in Construction Phase ====== ===== Work Breakdown Structure ===== The work breakdown structure (WBS) describes all project deliverables. 1 SONG in NM Construction *1.1 Project Management *1.1.1 NSF start (M) *1.1.2 WBS development and approval *1.1.3 Project schedule development and approval *1.1.4 MOU documents *1.1.5 Postdoc *1.1.6 Budget *1.1.7 Contracting *1.1.8 Reporting Documentation *1.2 Facilities *1.2.1 [[observatory_dome_and_pier|1-m dome]] *1.2.1.1 Preparation work *1.2.1.2 Telescope removal *1.2.1.3 Pier work *1.2.2 NMSU lab facility *1.2.3 APO lab facility *1.2.4 [[fiber_run|Fiber run]] *1.2.4.1 Design *1.2.4.2 Fabrication, procurement, installation *1.3 Telescope Systems *1.3.1 [[planewave_1000#Installation|PlaneWave 1000 1-m telescope (vendor)]] *1.3.2 Monitors *1.3.3 Remote communication system *1.3.3.1 Hardware *1.3.3.2 Observatory control system (OCS) *1.3.3.3 [[software|Telescope control system]] (TCS) *1.4 Instrument Systems *1.4.1 [[song_spectrograph|SONG spectrograph]] *1.4.1.1 Optical design *1.4.1.2 Standard item procurement *1.4.1.3 Specialty item procurement *1.4.1.4 Optical table *1.4.1.5 Lab assembly *1.4.1.6 Control computers and software *1.4.1.7 Thermal enclosure *1.4.1.8 Monitors *1.4.1.9 Lab testing and acceptance *1.4.1.10 Transport to APO *1.4.1.11 Reassembly and integration *1.4.1.12 Site testing and acceptance *1.4.2 [[focal_plane_unit|Guider unit]] *1.4.2.1 Design and assembly *1.4.2.2 Lab testing and acceptance *1.4.2.3 Transport to APO *1.4.2.4 Reassembly and integration *1.4.2.5 Site testing and acceptance *1.4.3 Calibration unit *1.4.3.1 Design and assembly *1.4.3.2 Lab testing and acceptance *1.4.3.3 Transport to APO *1.4.3.4 Reassembly and integration *1.4.3.5 Site testing and acceptance *1.4.4 Solar telescope (tbd) *1.5 Network Software *1.5.1 Scheduler *1.5.2 Data handling system (DHS) *1.5.3 Monitors database and webpage *1.6 Integration, Test, and Commissioning *1.6.1 Software integration *1.6.2 First light through telescope *1.6.3 First light through spectrograph *1.6.4 Science verification *1.6.5 NSF end *1.7 Contingency *1.7.1 Cost contingency *1.7.2 Schedule contingency *1.7.3 Scope contingency ===== Schedule ===== A high-level picture of the construction project schedule as of August, 2023 is shown here. {{:manage:project_schedule.png?direct&500 |}} ===== Update / item tracking ===== Tasks identified February 2025: Spectrograph - continued work on alignment, esp with "point" source - installation of prism - installation of camera - installation of focuser + detector - testing with calibration source? solar source? Calibration channel - assembly of relay optics / stage at focal plane - development of calibration source : Shelyak possibility? Selectable sources by stage? Integrating sphere? Fiber - getting long fiber run + ferrule. All circular fiber? match 125 micron cladding or not? Fusing 50/75/125 micron cladding onto other 50 micron fiber at focal plane side? Fusing hexagonal fiber onto circular 50 micron fiber at ferrule side? - running fiber through conduit Spectrograph room - legs for table - insulating box for spectrograph - making room in APO room - confirming power (UPS) and Ethernet - relay/thermocouple control/computer packaging - location of pump - more thermocouples for monitoring instrument FPU box - cover - cabling Dome - lower slit control - packaging of dome control - spare computer and Raspberry Pi? Software - interfacing Aarhus with APO