Attending: Nancy Chanover (NMSU), Bill Ketzeback (APO), Sarah Tuttle (UW), Chip Kobulnicky (UWy), Ben Williams (UW), Michael Hayden (OU), Misty Bentz (GSU), Eric Bellm (UW), Moire Prescott (NMSU)
The detailed site report is included below, followed by additional information discussed during today's meeting.
3.5-m Telescope and Instruments Highlights, 7/02/25 – 08/05/25
1) Overview
Summer shutdown activities occupied the first half of the month. Surprisingly in the second half of July we were able to get several nights of on-sky science despite the monsoon weather.
Reminder: We have position openings for 3.5m Chief Telescope Technologist (Engineer) and Mechanical Engineer, Lead. These positions close on August 15 so please spread the word.
Mechanical Engineer: https://careers.nmsu.edu/jobs/mechanical-engineer-ld-remote-locations-new-mexico-united-states
Chief Telescope Technologist: https://careers.nmsu.edu/jobs/chief-telescope-technologist-remote-locations-new-mexico-united-states
We will be hiring only one person but have two postings to reflect different academic degrees and experience levels; interested candidates should apply for the one that best matches their skill set and preparation.
2) Operations
3.5m Telescope: Telescope is working as expected. Seasonal motion errors have been more frequent. The tertiary rotation mechanism has experienced some issues after a software remapping of port positions. Further position refinements may be required.
0.5m Telescope: Telescope is working as expected. Users have experienced several camera problems with both FlareCam and dcamera-spare related to frosting/icing or inability to cool properly. Cary serviced dcamera-spare by replacing both cooling fans and recharging the CCD vessel with gas. The off-axis guider has not been very reliable, requiring power cycles.
KOSMOS: System is cooled and stable. Increased dark current for long exposures has been confirmed. We attempted a vacuum servicing of the cryostat but without much luck. We anticipate having to open the vacuum vessel in the clean room sometime during Quarter 4 2025 to investigate possible thermal shorts or opens. kcamera-ICC was backed up over shutdown.
ARCTIC: The diffuser rotation mechanism is still unreliable even after a full servicing. Troubleshooting is continuing. The mechanism that moves the diffuser in and out of the optical path is still functional in the meantime. The rest of the instrument is cooled. We replaced the ion pump cable and moved the controller back to the intermediate level.
Agile: The camera is non-operational; the thermoelectric cooler failed again. The camera is warm and we do not plan further repair work with this camera. We are planning on decommissioning the camera. The Agile instrument rotator is still not performing nominally and we are troubleshooting it further to prepare for SoonerCam.
ARCES: The CCD reservoir for the cooling system is currently warm and not usable for science. We are keeping the shield reservoir cold. During shutdown we did a vacuum servicing but shortly after cooling the inter-order light showed elevated contamination. We have taken it out of service to address this problem. Work continues on a replacement and modern ICC, and so far testing is going well. A commissioning report for the new ICC is being worked on.
DIS: System is warm and out of service. Decommissioning has begun.
NICFPS: System is cooled and usable. The ICC was backed up fully during shutdown.
TripleSpec: System is cooled and usable. The ICCs (tspec and tcamera) were backed up during shutdown. Tcamera-ICC experienced another failure of one of its RAID hard drives and it needed to be rebuilt.
APOLLO: A team from NASA returned to site this past month to address issues with optical alignment and laser power issues. The instrument is again available for laser ranging but additional work will need to be done upgrading the power measurement equipment and working on some of the thermal metrology.
All-Sky camera: 3.5m engineering staff has been working with the ALCOR manufacturer to remedy camera and software problems. Troubleshooting continues.
The summer shutdown is complete; it was fairly short this year. We accomplished daytime engineering in the first week and used the second week for on-sky engineering. All of the necessary baseline tasks in order to return the telescope to scientific operations were completed. This includes handwashing all the mirrors, a spring cleaning of the enclosure and instrumentation, greasing/lubricating various moving parts, and vacuum servicing KOSMOS and ARCES.
The KOSMOS servicing did not seem to alleviate the high dark current reported last month, so we may need to unseal the cryostats and go into the instrument to investigate it further. We currently plan to do this during Q4. The ARCES servicing went as expected; it was OK for a short time after cooling but then the inter-order light ratios plummeted (indicating lots of scattered light), which means the contamination migrated within the instrument. It will be taken back out of service to mitigate that over the next 1.5 weeks; we've already started that process, and the instrument should be available for use the night of August 22 (note added in proof: it was back on August 15!).
The 3.5m telescope is working as expected; the seasonal motion errors are more frequent but not unexpected given the current season.
The 0.5m telescope is working as expected but the cameras (FlareCam and dcam-spare) continue to have problems. There was a loss of vacuum in the CCD canisters, which resulted in frosting/icing within the dewar. Cary serviced dcam-spare and got it back to reliable performance but FlareCam is less reliable and continues to get worse with age.
APOLLO had numerous laser and optical alignment issues over the last month and a NASA team came back to the site to work on it. We believe the instrument is now functional but there may be additional work to be done to address a recently discovered laser frequency issue.
As a reminder, we have a current opening (covered by two different job postings) for the 3.5m chief telescope engineer. We are currently reviewing applications for telescope operator/support astronomer position.
The 3.5m schedule for Q3 has been in flux given the recent echelle engineering. Users who lost observing time due to the echelle servicing or weather are especially encouraged to request OPEN/DD time in Q3. To request this time please follow the standard procedure by emailing your request to Ben Williams, Russet McMillan, Amanda Townsend, Nancy Chanover, and your institutional scheduler.
All allocations for Q4 have been sent to the institutional schedulers; proposals are due on August 25. Note that the allocation emails stated that our ability to offer a virtual training in Q4 is uncertain due to staffing limitations; we indicated that we MAY offer it in Q4.
Next week is the only open week remaining in the ARCSAT Q3 schedule.
Please see the site report above.
Open action items from previous meetings:
New action items from this meeting:
None.
The next meeting will be on September 2, 2025 at 10:30 MDT.