 === Call for papers/grants info ===  === Call for papers/grants info === 
  
-Nancy issued her annual call for scientific papers and student theses/dissertations that make use of data acquired with the 3.5m and/or ARCSAT. Please send her all such papers (accepted or published) covering Jan. 1 2025 to present no later than July 31, 2027. New this year: Nancy is also collecting information concerning funding awards that have been enabled through access to the 3.5m. Please send her the following information for any APO-related grants: PI name, Funding Agency/Program, Project Title, Total Budget (if willing to share it), period of performance (years only), and relevant 3,5m instrument(s). This information will not be made public, but will be summarized for the ARC Board.+Nancy issued her annual call for scientific papers and student theses/dissertations that make use of data acquired with the 3.5m and/or ARCSAT. Please send her all such papers (accepted or published) covering Jan. 1 2025 to present no later than July 31, 2026. New this year: Nancy is also collecting information concerning funding awards that have been enabled through access to the 3.5m. Please send her the following information for any APO-related grants: PI name, Funding Agency/Program, Project Title, Total Budget (if willing to share it), period of performance (years only), and relevant 3.5m instrument(s). This information will not be made public, but will be summarized for the ARC Board.
  
 ---- ----
  
-=== Instrument initiatives ===  +=== New instrument initiatives === 
- +
-  * Ocotillo - Sarah reported progress on having the necessary parts in the shop, assembly is underway, software to control the camera is in work, and the first fiber bundle is in progress in the lab. All optics are in hand except for one, which she expects to receive in two weeks. The orange channel is ready for mechanical design. Once the red channel is in the building stage Caleb will shift to work on the orange channel. The blue channel is nearly optimized.+
  
 +  * Ocotillo - Sarah reported progress on having the necessary parts in the shop. Assembly is underway, software to control the camera is in work, and the first fiber bundle is in progress in the lab. All optics are in hand except for one, which she expects to receive in two weeks. The orange channel is ready for mechanical design. Once the red channel is in the building stage Caleb will shift to work on the orange channel. The blue channel is nearly optimized.
   * ASPEN - Work on the Atmospheric Dispersion Corrector is proceeding as it will be used with ARCES even before ASPEN is completed. The ASPEN Preliminary Design Review is scheduled for later this month. This will be an important milestone in refining and finalizing the instrument design.   * ASPEN - Work on the Atmospheric Dispersion Corrector is proceeding as it will be used with ARCES even before ASPEN is completed. The ASPEN Preliminary Design Review is scheduled for later this month. This will be an important milestone in refining and finalizing the instrument design.
 +  * SoonerCam: see site report for progress related to SoonerCam and the Agile rotator.
  
 ---- ----