=== Additional telescope and instrument discussion === | === Additional telescope and instrument discussion === | ||
- | The observatory has been hit with several snow storms that have significantly impacted observing over the past few weeks. The forecast is improving for the next week or so. March is shaping up to be a busy month: the UVa/DSSI team is here now, a CU class will be on site next week, and Sarah Tuttle will be here the week of March 20th for KOSMOS work. More visitors will be coming in Q2, so we expect to be remain quite busy through June. TUI work is continuing, with a Docker mode in the works. The ARCTIC diffuser has been acting up in cold weather; investigations into that issue are underway. The issue of the Agile time stamps in the image headers being incorrect is actively being worked on. The issue is with the trigger signal that comes from the high speed/high accuracy clock that's in the ICC machine. For users, this might be manifested as an error message, or it could affect header information even if there is no error message. The image time stamps are intended to be accurate to 0.01 s but currently there is no way to test that because the other machines are less accurate. Users should assume that the exact time stamps in their Agile image headers are unreliable, although the length of exposures and the photometry are both still fine. It is really just the precise timing that is affected; this issue started in mid-January. DIS scattered light is behaving as expected. There is a current issue with the TripleSpec instrument cart, which does not affect observing but does affect instrument fills during the day. As a result it could be taking | + | The observatory has been hit with several snow storms that have significantly impacted observing over the past few weeks. The forecast is improving for the next week or so. March is shaping up to be a busy month: the UVa/DSSI team is here now, a CU class will be on site next week, and Sarah Tuttle will be here the week of March 20th for KOSMOS work. More visitors will be coming in Q2, so we expect to be remain quite busy through June. |
+ | |||
+ | TUI work is continuing, with a Docker mode in the works. | ||
+ | |||
+ | Instrument updates: | ||
+ | |||
+ | * The ARCTIC diffuser has been acting up in cold weather; investigations into that issue are underway. | ||
+ | * The issue of the Agile time stamps in the image headers being incorrect is actively being worked on. The issue is with the trigger signal that comes from the high speed/high accuracy clock that's in the ICC machine. For users, this might be manifested as an error message, or it could affect header information even if there is no error message. The image time stamps are intended to be accurate to 0.01 s but currently there is no way to test that because the other machines are less accurate. Users should assume that the exact time stamps in their Agile image headers are unreliable, although the length of exposures and the photometry are both still fine. It is really just the precise timing that is affected; this issue started in mid-January. | ||
+ | * DIS scattered light is behaving as expected. | ||
+ | * There is a current issue with the TripleSpec instrument cart, which does not affect observing but does affect instrument fills during the day. As a result it could take longer to mount/ | ||
+ | |||
+ | Work is proceeding for getting the 3.5m mirror ready for realuminization at Lowell this summer. We heard from KPNO that they will not be able to accommodate any external mirrors at their coating chamber this summer, so it's good that we decided to proceed with having the work done at Lowell. | ||
---- | ---- | ||
Line 64: | Line 75: | ||
=== Data reduction software update === | === Data reduction software update === | ||
- | Davenport - still need update | + | In response to last month' |
- | Holtz - interest in data reduction software | + | |
- | Pyvista - pedagogical and simple, | + | Jon Holtzman presented an overview of pyvista, which he has been developing for several years. pyvista is intended to be a general |
- | For spectrographs - PypeIt - X Prochaska - significant cast of support characters | + | |
- | Nick PyReduce - Kevin - échelle software- we use CERES - Rafael Brom developed | + | Other options for reducing spectrograph data include PypeIt (developed by X. Prochaska with a significant number of supporting helpers) and PyReduce. |
- | Chip: is this a suitable teaching tool? Yes - used w/upper level undergrads/ grads | + | |
- | spectroscopy | + | |
- | propagates | + | |
- | Joanne expressed interest - | + | |
- | Eric B - tried to get PypeIt working with DIS but sort of succeeded - complex piece of software, ground to a halt - if someone wants to build on it it' | + | |
- | https:// | + | |
- | https:// | + | |
- | holtz@nmsu.edu | + | |
---- | ---- | ||
Line 82: | Line 85: | ||
=== Instrumentation update === | === Instrumentation update === | ||
- | Sarah: Ocotillo - preparing for PDR, in lab testing to finalize hardware prefs, Caleb putting together fiber feed connections for NA2 port, for MOS robot portion and IFU traditionally build bundles, looking instead at cleaved fibers working with collaborators at LBNL and then bundle them - hoping to keep throughput high across the bandpass. UC - we will let you know when preparing to do PDR w/mountain - summary to UC after that. | + | Nancy will be providing updates on various instrumentation initiatives every two months, or when otherwise needed. |
+ | Regarding Ocotillo, Sarah reported that she and her team are preparing for the Preliminary Design Review. They are conducting in-lab testing to finalize some hardware preferences. Caleb is putting together the fiber feed connections for the NA2 port. For the multi-object portion with robotically positioned fibers as well as for the integral field unit, traditionally one would build fiber bundles. Sarah, working with some collaborators at LBNL, is currently exploring the option of using cleaved fibers that would then be bundled, which would keep the throughput high across the entire bandpass. She will notify the Users Committee once they are preparing to do the PDR with the observatory staff and will provide summary documents to the Users Committee after that. | ||
+ | |||
+ | Plans for a multi-band imager are still being formulated, and require discussions with the UVa instrument team to flesh out how such an instrument would fit into their planned progression of instrument development efforts. | ||
+ | |||
+ | Regarding a new echelle spectrograph, | ||
+ | |||
+ | ---- | ||
=== Q1 3.5m scheduling === | === Q1 3.5m scheduling === | ||
- | There is one unassigned | + | There is one unassigned |
---- | ---- | ||
Line 93: | Line 103: | ||
=== Q2 3.5m scheduling === | === Q2 3.5m scheduling === | ||
- | 3 visiting instrument runs (2 instruments), 4 onsite | + | The Q2 schedule is in draft form and is nearly complete; we expect to be able to publish it before the end of this week. In Q2 we are expecting |
- | only have 1 person signed up for remote training | + | |
- | despite | + | We only have one person signed up for the Q2 remote training |
- | poll users, let us know ASAP | + | |
---- | ---- | ||
Line 102: | Line 111: | ||
=== Q1 ARCSAT scheduling === | === Q1 ARCSAT scheduling === | ||
- | Notify | + | The Q1 ARCSAT schedule has some open slots. **UC reps: please remind your users that they should notify |
---- | ---- | ||
Line 111: | Line 119: | ||
Open action items from previous meetings: | Open action items from previous meetings: | ||
- | * Nancy: make sure that the APO web site gets updated to address the issues reported by Eric B. in December. Status: OPEN. There were several | + | * Nancy: make sure that the APO web site gets updated to address the issues reported by Eric B. in December. Status: OPEN. There is one remaining |
* the wiki link on the 3.5m page still pointed to the old wiki - //this was fixed.// | * the wiki link on the 3.5m page still pointed to the old wiki - //this was fixed.// | ||
- | * the Search Site function on the APO home page does not work. //Testing is ongoing | + | * the Search Site function on the APO home page does not work. //A notice will be added to reflect the fact that this search tool will not work from computers outside of the APO VPN.// |
* the ToO policy is not easily found. //We are working on a document// that we can post on the scheduling page to make this information more easy to locate. | * the ToO policy is not easily found. //We are working on a document// that we can post on the scheduling page to make this information more easy to locate. | ||
- | * Nancy or Russet: get sample KOSMOS data from JHU user who reported scattered light issue. Status: | + | * Nancy or Russet: get sample KOSMOS data from JHU user who reported scattered light issue. Status: |
* Nancy: share communications plan re: new instrumentation with UC at next meeting. Status: CLOSED. | * Nancy: share communications plan re: new instrumentation with UC at next meeting. Status: CLOSED. | ||
* Nancy: get updated on pyKOSMOS and report to UC next month. Status: OPEN. | * Nancy: get updated on pyKOSMOS and report to UC next month. Status: OPEN. | ||
Line 122: | Line 130: | ||
New action items from this meeting: | New action items from this meeting: | ||
- | * xxx | + | * UC reps: notify your users about the option of using pyvista (and/or some of the other packages listed above) for data reduction. |
+ | * UC reps: notify your users that Nancy is seeking 1-2 more echelle users to participate in the tiger team charged with firming up the science requirements for a new echelle spectrograph. | ||
+ | * UC reps: poll your department users and if there is a need for a remote training in option for Q2, notify Russet ASAP (within the next day or so). | ||
+ | * UC reps: remind your users that they should notify us if their plans change and they wish to forfeit their week of scheduled ARCSAT time. | ||
---- | ---- |